Incident involving a container of metal waste
Incident report
May 25, 2004
On May 19, 2004, a container of fuel hulls and end-fittings that had been insufficiently filled was transferred from the R1 shearing facility to the ACC compaction facility* at the COGEMA La Hague UP2 plant.
The insufficient fill level was detected upon receipt of the drum in the ACC facility and was due to the uneven distribution of the metal materials in the container.
A proposal was made to French nuclear safety authority ASN (Autorité de Sûreté Nucléaire) to classify the incident as a level 1 event on the 7-level International Nuclear Event Scale (INES) for non-compliance with authorized operating parameters without impact on operating personnel or the environment.
*This facility compacts the remaining metal components of used fuel (hulls and end-fittings) after it has been sheared as well as dry active waste. The compacted waste is put into stainless steel containers.

Clip AREVA in MARCOULE
MELOX, world leader in the fabrication of MOX
Historical agreement in civil nuclear in India
Experts in dismantling
"La Hague : sûreté nucléaire et radioprotection en 2010" [FR]
AUSRA: a world leader in concentrated solar plants
Awarding -Project leaders for South Africa diplomas
Companies receiving the "AREVA Supplier Label"
Purifying and dispatching uranyl nitrate - Technical sheet